GoodWe GoodWe ET/EH/BH/BT Hybrid Inverter (grid) Modbus TCP template

GoodWe ET/EH/BH/BT Hybrid Inverter (grid)

The GoodWe ET/EH/BH/BT series are three-phase hybrid solar inverters with integrated battery storage support and built-in grid metering. This Modbus TCP template reads the inverter's internal grid meter, exposing total active power at the grid connection point, cumulative imported energy, per-phase active power on L1, L2, and L3, and per-phase grid currents. Connecting via the ModbusCloud Gateway gives installers and facility managers a live picture of import/export balance and phase loading without any additional external meter hardware.

Protocol
Modbus TCP
Connection
Ethernet, Modbus TCP
Registers
8, read only
Brand
GoodWe
Last updated

Registers (8)

8 read, 0 write

NameUnitAccessAddress (Hidden until you enter your email)Function (hidden)Type (hidden)
powerWRead
energykWhRead
powers_aWRead
powers_bWRead
powers_cWRead
currents_aARead
currents_bARead
currents_cARead

Loading registers…

Send your device list

If a device is not in the library yet, we build the template for free as soon as we have the register data.

Use cases

  • Monitor total grid import power in real time to verify that PV and battery are offsetting consumption as expected.
  • Track cumulative grid energy import over time to report on self-sufficiency ratios for building owners.
  • Alert on sustained negative total active power to confirm grid-export is within permitted feed-in limits.
  • Compare per-phase active power on L1, L2, and L3 to detect phase imbalance in a three-phase installation.
  • Verify per-phase grid currents after adding new loads to confirm the installation stays within cable ratings.

Installation

  1. Install the GoodWe LAN module or WiFi+LAN module in the inverter's communication port, replacing the default WiFi dongle, and confirm ARM firmware is version 13 or higher for HV battery models.

  2. Connect the LAN module to your local network via a switch or router, then assign a static IP address to the inverter through your router's DHCP reservation to prevent address changes after a power cycle.

  3. In the ModbusCloud portal, add the ModbusCloud Gateway to the same network segment, import the GoodWe ET/EH/BH/BT Hybrid Inverter (grid) template, and set the unit ID to 247 (the GoodWe factory default) and port to 502.

  4. Spot-check register 36025 in the live data view against the inverter's own display or the SEMS portal to confirm the total active power reading is consistent before saving the configuration.

Things to watch for

The gateway connects but all grid registers return zero or no data.

The inverter must be powered by DC (PV) or AC (grid) before Modbus communication becomes active. If the inverter is in standby with no power source it will not respond to queries. Confirm the LAN module is installed and that ARM firmware meets the minimum version requirement (13 for HV, 15 for LV).

Per-phase power values look correct but total power at 36025 is wrong.

Register 36025 is a signed 32-bit value spanning two consecutive 16-bit Modbus words. If your polling tool reads only one word you will get a truncated result. Ensure your Modbus client reads two registers starting at 36025 using function code 3, with high word first and low word second.

The portal loses connection to the inverter every few hours.

GoodWe recommends assigning a static IP to the LAN module via DHCP reservation. A dynamic address can change after a power cycle or DHCP lease renewal, causing the Gateway to lose the target. Also keep polling intervals at 10 seconds or longer to avoid overwhelming the inverter's communication stack.

Energy at register 36017 does not match the utility meter reading.

Register 36017 is the inverter's internal meter total import counter (float, kWh) and only starts accumulating from the date of commissioning. It also tracks import only, not export. Discrepancies against a utility meter are expected if energy was consumed before the inverter was installed or if the utility meter measures export differently.